One page. Every project. Problems first.

Why it's built this way · how I call health and run the weekly review

Problems sort to the top. Most leaders read the first three rows and stop, so those rows should be the ones that need them.

How I call health:

  • Green: on plan. No help needed.
  • Yellow: the date, scope or budget is at risk, but the team has a plan to recover.
  • Red: we will miss unless someone above the team makes a call.

Anything yellow or red has to carry a path to green. If nobody can say what gets it back on track, that is the problem to raise.

A status more than a week old gets flagged as stale. An old green tells you very little.

How I use it: I update it before the weekly leadership sync and walk the reds and yellows first. Click any project to see its risks in Foresight and its latest report in Briefly.